7 STATIONS JOINT VENTURE

7 STATIONS JOINT VENTURE2018-08-24T23:33:25+00:00

Project Description

Project
Improvement to 7 Stations, West End Line, Brooklyn
Owners contract number
A35797
Owners Name
NYCT
General description of the project type and size
Renovated key structural and architectural components of work at 7 above ground subway stations, including structural steel repairs to the Line structure between and adjacent to all stations.
Description of scope of work
Citnalta joint ventured with Judlau Contracting, Inc. and together they acted as the General Contractor responsible for supervising all of the subcontractors and/ or performed 100 percent of the contract work.

The Bay Parkway station, one of the 7 stations was completely renovated including its historic plaster and terracotta tile façade. All 7 stations received new rubbing board and tactile edges along with the new stairs from street level to the mezzanine and up to the platform.

Original Start and End dates of construction
The Contract was awarded in 8/2009 and the schedule provided for the project to be complete in 31months.
Actual Start and End dates of construction
Awarded in 8/2009

Completed in 05/2013

Dollar amount at award
$88,472,000.00
Dollar amount at completion
$92,814,566.00