Project Description

Project
P.S.11 Queens New 4 Story Addition, Upgrades of Services in the Existing School, and Rehabilitation of new playground
Owners Name
NYC School Construction Authority
General description of the project type and size
Citnalta will be constructing a new 5 story Addition to the existing school. In addition, Citnalta will be upgrading the existing building constructed in 1952.
Description of scope of work
Public School 11 is a multifaceted project which has three main components.

The first component is Phase 1, new 5 story addition. This addition will be approximately 85,000 SF, and will include new architectural finishes as well as new mechanical, electrical, and plumbing systems. The new addition will then be connected to the existing school. Phase 1 has a schedule of approximately 24 months for completion.

Phase 2 will commence following Phase 1 which includes installing new drainage and utilities as well as removing the existing play yard and creating a new athletic field for the school. This portion of the project will be approximately 12 months in duration. Working concurrently with the play yard the existing school will receive new architectural finishes. In addition to the new finishes the schools heating system will be installed.

Phase 3 will upgrade the existing fire alarm, electrical, plumbing and install a new sprinkler system within the existing school. This portion of the project is scheduled to be completed by October of 2018.

Original Start and End dates of construction
Phase 1: New 4 Story Addition June 2017

Phase 2: New Play yard and site-work improvements September 2018

Phase 3: Existing School Rehab and Boiler Replacement October 2018

Actual Start and End dates of construction
Phase 1: New 4 Story Addition, June 2017

Phase 2: New Play yard and site-work improvements, September 2018

Phase 3: Existing School Rehab and Boiler Replacement,  October 2018