Project Description
Project |
---|
PS70 Queens, New Addition and ADA Upgrade to Existing School |
Owners contract number |
C12604 |
Owners Name |
NYC School Construction Authority |
General description of the project type and size |
Citnalta together with its subcontractors built a new 5 story addition to the existing PS70 school and completed ADA upgrades throughout the existing school. |
Description of scope of work |
Build a New Addition and ADA Upgrade to Existing School. Project was split into three phases: Phase I – Kitchen Exhaust Work · Reroute kitchen exhaust flue · Remove existing kitchen Compressor Phase II – New Addition & Site Work · Build new 5-story addition · Site work around new addition Phase III – Existing School ADA Compliance, TCU and Remaining Site Work · Relocate TCU’s · Site work and detention system under TCU’s · ADA Compliance work in existing school |
Original Start and End dates of construction |
The NTP was issued on 7/17/2012 and the project was scheduled for completion in 36 months. |
Actual Start and End dates of construction |
Awarded on 7/17/2012 Completed on 7/09/2015 |
Dollar amount at award |
$42,702,000.00 |
Dollar amount at completion |
$44,213,626.00 |