PS70 Queens, New Addition and ADA Upgrade to Existing School
Owners contract number
C12604
Owners Name
NYC School Construction Authority
General description of the project type and size
Citnalta together with its subcontractors built a new 5 story addition to the existing PS70 school and completed ADA upgrades throughout the existing school.
Description of scope of work
Build a New Addition and ADA
Upgrade to Existing School.

Project was split into three phases:

Phase I – Kitchen Exhaust Work

· Reroute kitchen exhaust flue

· Remove existing kitchen

Compressor

Phase II – New Addition & Site Work

· Build new 5-story addition

· Site work around new addition

Phase III – Existing School ADA

Compliance, TCU and Remaining Site

Work

· Relocate TCU’s

· Site work and detention system under TCU’s

· ADA Compliance work in existing school

Original Start and End dates of construction
The NTP was issued on 7/17/2012 and the project was scheduled for completion in 36 months.
Actual Start and End dates of construction
Awarded on 7/17/2012
Completed on 7/09/2015
Dollar amount at award
$42,702,000.00
Dollar amount at completion
$44,213,626.00