Project
P.S.89 Brooklyn, Design/Build a New 4 Story School with Full Cellar
Owners contract number
C11190
Owners Name
NYC School Construction Authority
General description of the project type and size
Citnalta together with its design sub-consultant, JCA Architects and subcontractors designed and built a new 65,000 square foot school.
Description of scope of work
Design–Builder responsible for supervising JCA Architects, the design sub-consultant and all of the trades and/ or performed 100 percent of the contract work. The project was completed in an aggressive 18 month schedule from start to design turnover to SCA. Citnalta worked adjacent to the LIRR tunnel and was required to take extra precaution during the foundation and support of excavation operation.
Original Start and End dates of construction
The NTP was issued on 11/14/2008 and the project was scheduled for completion in 18 months.
Actual Start and End dates of construction
Awarded on 11/14/2008

Completed on 8/25/2010

Dollar amount at award
$37,199,000.00
Dollar amount at completion
$37,799,147.00