Citnalta-TAP Joint Venture successfully reached substantial completion on MTA C&D/New York City Transit's Design and Construction of Accessibility Upgrades at Livonia Avenue Station on the Canarsie Line in the Borough of Brooklyn.
The JV team installed two new elevators and reconfigured the street context around the station entrance, opened the control area and modified the agent booth to conform the station to ADA requirements. They also installed a new transfer passageway above the platforms that provides accessibility between the northbound and southbound trains.
Other work items included:
State-of-good-repair steel repairs, top and bottom flanges, stiffeners, bracing and bolt replacement
Hoist way façade installation, including glazing, aluminum composite panels, louvers and stainless-steel panels
Signals support messengers and final cable routing
EPDM and standing seam roofing and leader installations
New sidewalks, ADA ramps and back-of-house exterior slabs
Bird deterrent installations
Milling and paving at the intersection between Van Sinderen and Livonia Avenues.
Congratulations to the Citnalta-TAP team!